The City of Brandon said in an emailed news release, “the new northbound bridge structures will be open to traffic today (Sept 13) and will accommodate one lane in each travel direction for the duration of construction of the southbound lanes and southbound bridges.
Other Key Notes:
-Fred Brown Way will be closed from 18th Street N to 19th Street N
-The east leg of Pacific Avenue including the under-bridge loop will reopen to traffic with the west leg of Pacific Avenue closed to accommodate construction
-Access to businesses and residences will be maintained at all times with temporary access provided as required during construction
-The new multi-use pathway and bridge structure will be open to accommodate active transportation (pedestrians, etc.) throughout the project.”
The entire Daly Overpass project is scheduled to be completed by the end of summer 2024.